Holiday Inn Express, Mascot – ProInvest
When with a previous employer, Paul was engaged by the client to act as lead Structural Engineer and Engineering Design Coordinator for the development of a new 10 storey hotel in Mascot.
The project was ‘fast-tracked’ through Development Approvals, design documentation and tender, which was complicated by the site being split across two separate titles, with 80% of the building on one title and the remainder on the adjoining. Because of uncertainties over approvals, it proved necessary to design the building for staged construction, with options included for the building to be stable and operable if only one stage was approved.
The development included a two level basement, excavating below the water table into saturated sand. With time as the driver, traditional shoring solutions involving soldier piles were discounted. Instead, we developed a wall system based on a permanent steel sheet pile wall, faced with shotcrete and waterproofed internally, The structure was then designed to be supported on a series of screw piles, which were restrained by a hydrostatic basement slab designed to resist uplift water pressures.
Again with speed of erection in mind, the upper floors were designed and constructed from precast concrete beam elements, supported on precast concrete walls between rooms. The building façade was designed by the Architect to be a precast concrete finish. Paul developed an arrangement of precast panels and a sequence of erection in conjunction with construction of each floor, such that the panels would provide critical edge protection as construction of each floor progressed, without the need for costly and time-consuming external scaffold systems.
Throughout the construction phase, Paul worked closely with builder, ADCO Constructions, to ensure that quality control of installations was achieved and issues were addressed in a timely manner to allow construction momentum to be maintained.